RESEARCH ON INFLUENCE OF KEY PARAMETERS OF DYNAMIC PROCESS OF SUBMARINE CABLE LAYING FOR OFFSHORE WIND POWER

Xu Chihao, Ren Nianxin, Li Jun, Luo Yunfeng

Acta Energiae Solaris Sinica ›› 2026, Vol. 47 ›› Issue (6) : 261-266.

PDF(3768 KB)
Welcome to visit Acta Energiae Solaris Sinica, Today is
PDF(3768 KB)
Acta Energiae Solaris Sinica ›› 2026, Vol. 47 ›› Issue (6) : 261-266. DOI: 10.19912/j.0254-0096.tynxb.2025-0062

RESEARCH ON INFLUENCE OF KEY PARAMETERS OF DYNAMIC PROCESS OF SUBMARINE CABLE LAYING FOR OFFSHORE WIND POWER

  • Xu Chihao1, Ren Nianxin1, Li Jun2, Luo Yunfeng2
Author information +
History +

Abstract

Based on the catenary theory and the lumped mass method, a comparative analysis of the dynamic response characteristics of submarine cables under diverse laying modes is carried out. Special attention is given to the sensitivity analysis of pivotal parameters, including wave direction, laying depth, touchdown point distance, and laying speed during the dynamic laying process of submarine cables. Thereby, the influence mechanism of each key parameter in submarine cable laying is unveiled. By contrasting the maximum effective tension and minimum bending radius of submarine cables under different laying methods, the dynamic response traits of various laying methods are elaborated.

Key words

offshore wind power / submarine cable / electric cable laying / effective tension / bending radius / dynamic response / parameter sensitivity

Cite this article

Download Citations
Xu Chihao, Ren Nianxin, Li Jun, Luo Yunfeng. RESEARCH ON INFLUENCE OF KEY PARAMETERS OF DYNAMIC PROCESS OF SUBMARINE CABLE LAYING FOR OFFSHORE WIND POWER[J]. Acta Energiae Solaris Sinica. 2026, 47(6): 261-266 https://doi.org/10.19912/j.0254-0096.tynxb.2025-0062

References

[1] 王裕霜. 国内外海底电缆输电工程综述[J]. 南方电网技术, 2012, 6(2): 26-30.
WANG Y S.Review on submarine cable projects for power transmission worldwide[J]. Southern power system technology, 2012, 6(2): 26-30.
[2] 黄小卫, 李晓骏, 左干清. 国内外海底电缆工程现状及展望[J]. 电线电缆, 2023, 66(1): 1-6.
HUANG X W, LI X J, ZUO G Q.Application status and prospect of submarine cable projects at home and abroad[J]. Electric wire & cable, 2023, 66(1): 1-6.
[3] TAORMINA B, BALD J, WANT A, et al.A review of potential impacts of submarine power cables on the marine environment: Knowledge gaps, recommendations and future directions[J]. Renewable and sustainable energy reviews, 2018, 96: 380-391.
[4] SHEN J Y, LIANG Y J, HONG H B, et al.Numerical investigation of burial depth effects on tension of submarine power cables[J]. Journal of marine science and engineering, 2024, 12(11):1972-1972.
[5] REDA A M, AL-YAFEI A M S, HOWARD I M, et al. Simulated in-line deployment of offshore rigid field joint: a testing concept[J]. Ocean engineering, 2016, 112: 153-172.
[6] 曹淑刚, 张吉, 孙小钎, 等. 考虑弯曲刚度的高压海缆敷设受力分析[J]. 太阳能学报, 2019, 40(10): 3009-3016.
CAO S G, ZHANG J, SUN X Q, et al.Tension analysis of high voltage submarine cable laying considering bending stiffness[J]. Acta energiae solaris sinica, 2019, 40(10): 3009-3016.
[7] 李健华, 黄亚珏, 李争霖, 等. 基于Fluent-OrcaFlex联合数值模型的海上风电场海底电缆冲刷及应力状态研究[J]. 太阳能学报, 2024, 45(10): 574-579.
LI J H, HUANG Y J, LI Z L, et al.Research on scouring and stress state of submarine cable in offshore wind farm based on Fluent-OrcaFlex joint numerical model[J]. Acta energiae solaris sinica, 2024, 45(10): 574-579.
[8] ZHANG D P, BAI Y, ZHAO W Q, et al.Dynamic analysis of submarine cable during the process of laying back to the seabed[J]. Ships and offshore structures, 2020, 15(2): 153-161.
[9] ZHANG D P, ZHAO B W, ZHU K Q, et al.Dynamic analysis of towed cable with variable length during turning maneuvers[J]. Scientific reports, 2023, 13: 3525.
[10] TRAPPER P A.Feasible numerical method for analysis of offshore pipeline in installation[J]. Applied ocean research, 2019, 88: 48-62.
[11] KUANG J X, CHEN G D, YUAN Z L, et al.Dynamic interactions of a cable-laying vessel with a submarine cable during its landing process[J]. Journal of marine science and engineering, 2022, 10(6): 774.
[12] LYU C, ZHOU X Q, LIU S.Analysis of weighted factors influencing submarine cable laying depth using random forest method[J]. Applied sciences, 2024, 14(18): 8364-8364.
[13] LU Q Z, FAN Y M, SU Q, et al.Study on contact force between umbilical and overboarding chute in deepwater S-lay process[J]. Ocean engineering, 2024, 302: 117693.
[14] HU J P, LI Z L, ZHANG Y Q.Numerical study on initial laying process of submarine cables for wave energy booster station in real sea states[J]. Journal of coastal research, 2020, 99(S1): 60-66.
[15] 吴庆华, 马凌, 岳浩, 等. 500 kV海南联网工程海底电缆线路设计[J]. 上海电气技术, 2021, 14(3): 5-9, 43.
WU Q H, MA L, YUE H, et al.Design of submarine cable line of 500 kV Hainan power link project[J]. Journal of Shanghai electric technology, 2021, 14(3): 5-9, 43.
[16] 邓卫红, 刘凡. 多波束系统在500 kV福港线海底电缆路由地形变化分析中的应用[J]. 南方能源建设, 2019, 6(增刊1): 119-123.
DENG W H, LIU F.Application of multibeam system in the analysis of the terrain change of the 500 kV Fugang high-voltage submarine cable[J]. Southern energy construction, 2019, 6(S1): 119-123.