LOW-VOLTAGE RIDE-THROUGH IMPROVEMENT STRATEGY FOR INVERTER-INTERFACED DISTRIBUTED GENERATION CONSIDERING SECONDARY VOLTAGE DIPS

Dai Zhihui, Zhang Yu, Xu Dongrui, Han Tao, Yu Haiping

Acta Energiae Solaris Sinica ›› 2026, Vol. 47 ›› Issue (12) : 225-232.

PDF(1819 KB)
Welcome to visit Acta Energiae Solaris Sinica, Today is
PDF(1819 KB)
Acta Energiae Solaris Sinica ›› 2026, Vol. 47 ›› Issue (12) : 225-232. DOI: 10.19912/j.0254-0096.tynxb.2025-1013

LOW-VOLTAGE RIDE-THROUGH IMPROVEMENT STRATEGY FOR INVERTER-INTERFACED DISTRIBUTED GENERATION CONSIDERING SECONDARY VOLTAGE DIPS

  • Dai Zhihui1, Zhang Yu1, Xu Dongrui1, Han Tao2, Yu Haiping2
Author information +
History +

Abstract

To address the issue of adjacent-line inverter-interfaced distributed generation(IIDG) disconnection caused by secondary voltage dips at the point of common coupling(PCC) after front-accelerated auto-reclosing operates on a permanent fault, an improved low-voltage ride-through(LVRT) strategy applicable to the distribution network with reclosers is proposed. Based on the LVRT specifications of IIDG, the impact of auto-reclosing on LVRT is analyzed, and the successful LVRT process is divided into three stages (voltage dip, voltage recovery, and power restoration). Prior to auto-reclosing actuation, the adjacent-line IIDGs terminate the ongoing LVRT process in advance by identifying these stages. When secondary voltage dips occur due to front-accelerated auto-reclosing on a permanent fault, the adjacent line IIDGs can initiate a new LVRT cycle to prevent grid disconnection. Simulation results verify that the proposed strategy avoids IIDG disconnection during secondary voltage dips without altering the original fault recovery scheme, exhibiting high practical value.

Key words

distribution networks / reclosers / voltage dips / inverter-interfaced distributed generation / low-voltage ride-through / fault recovery

Cite this article

Download Citations
Dai Zhihui, Zhang Yu, Xu Dongrui, Han Tao, Yu Haiping. LOW-VOLTAGE RIDE-THROUGH IMPROVEMENT STRATEGY FOR INVERTER-INTERFACED DISTRIBUTED GENERATION CONSIDERING SECONDARY VOLTAGE DIPS[J]. Acta Energiae Solaris Sinica. 2026, 47(12): 225-232 https://doi.org/10.19912/j.0254-0096.tynxb.2025-1013

References

[1] 丁明, 胡迪, 毕锐, 等. 含高渗透率可再生能源的配电网可靠性分析[J]. 太阳能学报, 2020, 41(2): 194-202.
Ding M, Hu D, Bi R, et al.Reliability analysis of distribution system containing high penetration renewable energy[J]. Acta Energiae Solaris Sinica, 2020, 41(2): 194-202.
[2] 文继锋, 刘子俊, 周专, 等. 新型电力系统下高渗透新能源接入的次同步振荡问题研究[J]. 太阳能学报, 2024, 45(11): 50-60.
Wen J F, Liu Z J, Zhou Z, et al.Research on sub-synchronous oscillation problem with high permeability new energy access in new power system[J]. Acta Energiae Solaris Sinica, 2024, 45(11): 50-60.
[3] 王增平, 林一峰, 王彤, 等. 电力系统继电保护与安全控制面临的挑战与应对措施[J]. 电力系统保护与控制, 2023, 51(6): 10-20.
Wang Z P, Lin Y F, Wang T, et al.Challenges and countermeasures to power system relay protection and safety control[J]. Power System Protection and Control, 2023, 51(6): 10-20.
[4] 栾琨, 戴志辉, 史琛. 应对10 kV配电网电流保护失配问题的整定优化方案[J]. 电力系统保护与控制, 2024, 52(15): 155-166.
Luan K, Dai Z H, Shi C.A setting optimization scheme to address current protection mismatch in a 10 kV distribution network[J]. Power System Protection and Control, 2024, 52(15): 155-166.
[5] 陈晓乾, 秦文萍, 杨乐, 等. 逆变式电源接入下的配电网自适应距离保护方案[J]. 电力系统保护与控制, 2023, 51(11): 27-38.
Chen X Q, Qin W P, Yang L, et al.Adaptive distance protection scheme for a distribution network given access of inverter power supply[J]. Power System Protection and Control, 2023, 51(11): 27-38.
[6] 彭生江, 陆军, 张中丹, 等. 光伏接入对电网的影响研究[J]. 电力系统保护与控制, 2021, 49(5): 157-164.
Peng S J, Lu J, Zhang Z D, et al.Research on the influence of photovoltaic access on a power grid[J]. Power System Protection and Control, 2021, 49(5): 157-164.
[7] 戴志辉, 柳梅元, 韦舒清, 等. 基于超导磁储能的光伏场站送出线路距离保护[J]. 中国电力, 2024, 57(10): 102-114.
Dai Z H, Liu M Y, Wei S Q, et al.Distance protection for outgoing line of photovoltaic station based on superconducting magnetic energy storage[J]. Electric Power, 2024, 57(10): 102-114.
[8] Tang M N, Lu H, Li B.Fault location of untransposed double-circuit transmission lines based on an improved Karrenbauer matrix and the QPSO algorithm[J]. Protection and Control of Modern Power Systems, 2023, 8(1): 44.
[9] 张展, 肖晃庆, 刘文泽, 等. 基于运行短路比的新能源场站换流器模式切换技术研究[J]. 太阳能学报, 2025, 46(7): 279-289.
Zhang Z, Xiao H Q, Liu W Z, et al.Research on mode switching technology of voltage-source converters in energy stations based on operating short-circuit ratio[J]. Acta Energiae Solaris Sinica, 2025, 46(7): 279-289.
[10] 高亮, 郎陈杰, 夏能弘. 分布式电源并网条件下配电网继电保护方案设计[J]. 电力系统保护与控制, 2017, 45(18): 143-149.
Gao L, Lang C J, Xia N H.Design of relay protection scheme of distribution network with DG[J]. Power System Protection and Control, 2017, 45(18): 143-149.
[11] 温智平, 梁振锋, 彭书涛, 等. 分布式电源接入对操作型自动装置影响研究综述[J]. 电网与清洁能源, 2017, 33(12): 123-128.
Wen Z P, Liang Z F, Peng S T, et al.An overview of researches of the influence of distributed resources on the operation-type automatic device[J]. Power System and Clean Energy, 2017, 33(12): 123-128.
[12] 戴志辉, 刘钧溢, 柳梅元, 等. 适用于IIDG接入的配网电流保护改进方案研究[J]. 太阳能学报, 2025, 46(6): 367-375.
Dai Z H, Liu J Y, Liu M Y, et al.Research on improved scheme of distribution network current protection applicable to inverter-interfaced distributed generator access[J]. Acta Energiae Solaris Sinica, 2025, 46(6): 367-375.
[13] 杨彬, 贾科, 李俊涛, 等. 基于电压上升限时检测的含新能源配电网自适应重合闸[J]. 电力系统自动化, 2023, 47(22): 66-74.
Yang B, Jia K, Li J T, et al.Adaptive reclosing of distribution network with renewable energy based on voltage rise time limit detection[J]. Automation of Electric Power Systems, 2023, 47(22): 66-74.
[14] 刘健, 张志华, 芮俊, 等. 一二次配合的配电线路自适应重合闸[J]. 电力系统保护与控制, 2020, 48(22): 26-32.
Liu J, Zhang Z H, Rui J, et al.Adaptive reclosing of distribution lines based on primary and secondary device coordination[J]. Power System Protection and Control, 2020, 48(22): 26-32.
[15] 邵文权, 刘一璇, 关欣, 等. 一种主动探测式的配电网相间重合前永久性故障判别方案[J]. 电力系统保护与控制, 2021, 49(14): 96-103.
Shao W Q, Liu Y X, Guan X, et al.An active detection scheme for permanent fault identification before phase-to-phase reclosing in a distribution network[J]. Power System Protection and Control, 2021, 49(14): 96-103.
[16] 郑晨玲, 朱革兰, 兰金晨, 等. 逆变型分布式电源接入对电压时间型馈线自动化的影响分析[J]. 电力系统保护与控制, 2020, 48(1): 112-116.
Zheng C L, Zhu G L, Lan J C, et al.Research on the effect of inverter interfaced distributed generation on voltage-time feeder automation[J]. Power System Protection and Control, 2020, 48(1): 112-116.
[17] 胡雪凯, 张乾, 胡文平, 等. 分布式光伏对线路自动重合闸的影响分析[J]. 电力系统保护与控制, 2019, 47(17): 75-82.
Hu X K, Zhang Q, Hu W P, et al.Analysis of the influence of distributed photovoltaic on automatic reclosing[J]. Power System Protection and Control, 2019, 47(17): 75-82.
[18] 李育强, 王志文, 王维庆, 等. 具备LVRT能力的光伏接入配网对重合闸的影响及对策[J]. 电力系统保护与控制, 2016, 44(15): 61-67.
Li Y Q, Wang Z W, Wang W Q, et al.Influence of PV with LVRT capability access to distribution network on automatic reclosing and its countermeasures[J]. Power System Protection and Control, 2016, 44(15): 61-67.
[19] 王若琪, 胡炎, 杨增力, 等. 大量分布式电源接入的配电网自适应重合闸及故障恢复策略[J]. 上海交通大学学报, 2026, 60(1): 42-50.
Wang R Q, Hu Y, Yang Z L, et al.Adaptive reclosing and fault recovery strategies for large scale distributed generation access in distribution networks[J]. Journal of Shanghai Jiao Tong University, 2026, 60(1): 42-50.
[20] 王志涛, 武志刚, 高厚磊, 等. 重合闸与低电压穿越相配合的有源配电网故障恢复方案[J]. 电力系统保护与控制, 2019, 47(3): 81-87.
Wang Z T, Wu Z G, Gao H L, et al.A fault recovery scheme cooperating with reclosing and LVRT for active distribution network[J]. Power System Protection and Control, 2019, 47(3): 81-87.
[21] 戴志辉, 柳梅元, 于海平, 等. 基于多维小波变换的新型有源配电网自适应重合闸方案[J]. 华北电力大学学报(自然科学版), 2026, 53(2): 119-131.
Dai Z H, Liu M Y, Yu H P, et al.Adaptive reclosing scheme of new active distribution network based on multi-dimensional wavelet transform[J]. Journal of North China Electric Power University (Natural Science Edition), 2026, 53(2): 119-131.
[22] GB/T 19964—2012 光伏发电站接入电力系统技术规定[S].
GB/T 19964—2012 Technical requirements for connecting photovoltaic power station to power system[S].