适用于光伏直流升压变换器的故障诊断及保护策略

张鑫宇1,2, 樊艳芳1, 马健2, 王一波3   

  1. 1.新疆大学电气工程学院,乌鲁木齐 830046;
    2.国网新疆电力有限公司电力科学研究院,乌鲁木齐 830011;
    3.中国科学院电工研究所,北京 100190
  • 收稿日期:2021-05-11 出版日期:2022-11-28 发布日期:2023-05-28
  • 通讯作者: 樊艳芳(1971—),女,硕士、教授、博士生导师,主要从事可再生能源并网技术及电力系统保护方面的研究。410849062@qq.com
  • 基金资助:
    新疆维吾尔自治区高校科研重点项目(XJEDU2021I009)

FAULT DIAGNOSIS AND PROTECTION STRATEGY FOR PHOTOVOLTAIC DC-DC CONVERTER

Zhang Xinyu1,2, Fan Yanfang1, Ma Jian2, Wang Yibo3   

  1. 1. School of Electrical Engineering, Xinjiang University, Urumqi 830046, China;
    2. State Grid Xinjiang Electric Power Co., Ltd. Electric Power Research Institute, Urumqi 830011, China;
    3. Institute of Electronic Engineering, Chinese Academy of Science, Beijing 100190, China
  • Received:2021-05-11 Online:2022-11-28 Published:2023-05-28

摘要: 以输入并联输出串联(IPOS)型Boost全桥隔离变换器(BFBIC)为研究对象,针对其内部故障发生后无法迅速定位的问题,提出基于波形积分法的故障诊断策略。该策略通过选取变换器内部固定测量点,基于运行机理分析变换器发生硬故障或直流汇集线路故障时各电气量的波形特征,并通过总结特征规律对故障位置进行识别。针对现有冗余桥臂方案在BFBIC-IPOS上不适用的问题,提出利用冗余升压单元实现内部故障穿越的保护策略。该策略通过更改器件参数及冗余单元备用状态,避免升压单元投切过程中的过流、过压问题。最后,通过PSIM建模仿真,验证故障诊断策略及冗余保护策略的有效性。

关键词: 光伏发电, DC-DC变换器, 故障分析, 故障诊断, 故障穿越

Abstract: Taking the input-parallel output-series(IPOS)type boost full bridge isolated converter(BFBIC)as the research object. Aiming at the problem that its internal fault cannot be located quickly after it occurs,a fault diagnosis strategy based on the waveform integration method is proposed. This strategy selects fixed measuring points inside the converter, analyzes the waveform characteristics of each electrical quantity when the converter has a hard fault or a DC collection line fault based on the operating mechanism, and identifies the fault location by summarizing the characteristic rules. Aiming at the problem that the existing redundant bridge arm scheme is not applicable to BFBIC-IPOS, a protection strategy using redundant boost units to achieve internal fault ride-through is proposed. This strategy avoids over-current and over-voltage problems in the switching process of the boost unit by changing the device parameters and the standby state of the redundant unit. Finally,through PSIM modeling and simulation,the effectiveness of the fault diagnosis strategy and the redundancy protection strategy is verified.

Key words: photovoltaic power generation, DC-DC converters, failure analysis, fault diagnosis, fault ride-through